Island Grove Community Event Center - Colorado Farm Show
Greeley, CO
| General Contractor: | Lefever Building Systems |
|---|
| Pre-Engineered Metal Building: | Varco Pruden Buildings |
|---|
| Supply & Erection: | Lefever Building Systems |
|---|
| Project Time Frame: | November 2004 - December 2005 |
|---|
| Project Turnkey Cost: | $6,289,650 |
|---|
LBS Project Management Details
- Steel Building Erection done by Lefever Building Systems in House Crews.
- 20,000 Man Hours to Frame, Insulate, Sheet and Trim out.
- Chief Industries Pre-Engineered Steel Building.
- Full tenant finish including offices, industrial kitchens, Ticketing, Restrooms (200 x 300 x 24'; 80,000 square feet).
- 3- 40x50 Cupolas on top of the Arena Roof with an overall height of 46'.
- Over 41 miles of Electrical wiring.
- Custom pre cast panels revealing the Pawnee Buttes.
- Sound Systems with 30 JBL speakers, 44 Lowell speakers and 12 JBL amplifiers.
- Over 5,000 cubic yards, ( LBS concrete finished 20,000 Sq. ft. flat work per day
- Exterior site improvements and parking lot.
- Project on time and under budget.