Bestway Batch Plant - Denver, CO

Denver, CO

Lefever Building Systems:Supply and Erection
Project Time Frame:April - November, 2003
Supply/Erect Cost:$368,776

 

Overview of Project: On this project we evaluated the prototype design we created for the Milliken Batch Plant for buildability and cost effectiveness and tweaked this design accordingly. We used a Gable Roof with a 4:12 slope and added a cupula with clear wall panels and louvers for passive solar light and ventilation. The flatter roof allowed the roof to be installed from the roof deck. The three silos are outside the building and do not penetrate the roof.

Key Building Features: