Enterprise CTF Compressor Station

Meeker, CO

Project Time Frame:June 2008 – November 2008
Project Turnkey Cost:$1,922,000.00
Supply and Erection:Lefever Building Systems

 

Project Overview: Multiple Building at a new Compressor Station including Office, South process, North process and Compressor Building

Key Building Features: All Building and components were Juniper Green in color, 68 x 52 South Process building, 68x126 North Process Building, 77x243 Compressor building, 40x100 Office building with all electrical, mechanical, plumbing, tenant finish work. Buildings are near Meeker, Colorado. Buildings have multiple cranes by Wazee crane.

Details on Steel Buildings:
Roof Panels: 26 gauge, Panel Rib roof, Special Color-Juniper Green Wall Panels: 26 gauge, Panel Rib walls, Special Color---Juniper Green