Division Headquarters Complex – Increment 1

Fort Carson, CO

Architect:CH Guernsey & Co.; Oklahoma City, Oklahoma
General Contractor:Blueline / PCL A Joint Venture
Pre-Engineered Metal Building:VP Buildings
Supply:Lefever Building Systems
Erection:Systems Contractors Inc. (under subcontract with Lefever Building Systems)
Project Time Frame:April 2008 – October 2008
Project Metal Building Subcontract Value:$462,052

 

Project Overview:
New Battalion Headquarters Building. 124'-8" x 113'-8" x 13'-0" with a 3:12 gabled pitched roof with a 20'-0" x 17'-6" x 13'-0" covered entry area with a 4:12 gabled pitched roof.

Scope:
New Headquarters building features a Dutch Hip roof on the front of the building. All walls were metal stud framed with split faced masonry to 3'-6" high and red masonry brick to eave line. Gable area on front and rear of building was a standard stucco EFIS in a beige color. Building had a 1'-0" eave extension on the front and both sides with 24 ga. VP, FP-12 soffit panels in Leaf Green color. Rear wall was a standard gable condition. Roof panels were 24 ga,VP, SLR, 2" high vertical seam Standing Seam roof panels in VP Leaf Green color. Two rows of SnoBar for snow retention were installed on the front and both sides of the roof. Roof included one each 4' x 4' Roof exhaust fan with curb. The standing seam roof system included a written 20 year finish and weather tightness factory warranty. Roof was insulated with a 9 1⁄2" (R-30) Cavity roof system utilizing Sky Web II (Fall Protection) supplied by Bay Insulation.

Details on Steel Buildings:
Roof Panels: 24 ga "SLR" Standing Seam; Color: Leaf Green
Soffit Panels: 24 ga "FP-12": Color: Leaf Green
Walls: masonry block, masonry brick & EFIS
Insulation: 9 1⁄2" (R-30) roof "Cavity" System with Sky Web II